top of page
Osseo Group logo

Site Requirements for all UP3D Equipment Installations.

  • Writer: Stuart Anderton
    Stuart Anderton
  • 3 days ago
  • 4 min read

This article outlines the site requirements for installation of your UP3D milling system and associated equipment. Please review each section carefully and ensure all requirements are met prior to the installation date. Proper preparation will allow us to complete installation, calibration and training without delays, so you can start using your system as soon as possible.


Furnaces

F30 - Porcelain Furnace

  • 600mm counter top depth required

  • 300mm clearance left/right of furnace required

  • No overhead cabinets

  • 10 Amp outlet - 15 Amp preferred

  • No power board allowed


F20 - Sintering Furnace

  • 600mm counter top depth required

  • 300mm clearance left/right of furnace required

  • No overhead cabinets

  • 15 Amp outlet required

  • No power board allowed

Fxx - Speed Sintering Furnace (not yet available)

  • 600mm counter top depth required

  • 300mm clearance left/right of furnace required

  • No overhead cabinets

  • 15 Amp outlet required

  • No power board allowed


Milling Machines


P55D - Dry single disk milling machine

  • 700-800mm counter top depth required

  • 600mm machine width

  • 400mm clearance left/right of mill required

  • Counter must be able to support 120kg without bowing

  • 10 Amp outlet

  • 1x ethernet connection to router/switch

  • Compressed air is not required (Air gun within reach is ideal for cleaning but not essential)

P53DC - Dry 12 disk changing milling machine

  • 800-1000mm counter top depth required

  • 1000mm machine width

  • 400mm clearance left/right of mill required

  • Counter must be able to support 150kg without bowing

  • 10 Amp outlet

  • 1x ethernet connection to router/switch

  • 1/4" PE tube connection to dry compressed air delivered at up to 100 L/min

  • Air gun within reach is ideal for cleaning but not essential

P42PLUS - wet block milling machine

  • 600mm counter top depth required

  • 600mm machine width

  • 400mm clearance left/right of mill required

  • Counter must be able to support 80kg without bowing

  • 10 Amp outlet

  • 1x ethernet connection to router/switch

  • Compressed air is not required (Air gun within reach is ideal for cleaning but not essential)

ICORE 5X - Titanium milling machine

  • 600x600mm floor space required

  • 2200mm vertical space required

  • 400mm clearance left/right of mill

  • 3x 10 Amp outlets - 15 Amp preferred

  • No power board allowed

  • 1x ethernet connection to router/switch

  • 1/4" PE tube connection to dry compressed air delivered at up to 100 L/min

  • Air gun within reach is essential for cleaning

Bench Size

If your bench is not large enough, we will install, provision and calibrate the mill on the floor. Once you have the correct cabinetry in place, you can move the unit yourself. No recalibration or service visit is required.


Network Requirements

If you only have a single ethernet port available, you will need a network switch.Please arrange this with your IT provider before installation. We will bring a switch and spare cable on the day as a backup, however if it is left on site there is a $400 charge. It is better to have this sorted in advance. Compressor If compressed air is required, it must be provided by a suitable standalone compressor, similar to the unit available from Sydney Tools HERE. You can order directly and have it delivered to your clinic or lab ahead of the installation date. The compressor used for your dental chairs will not be suitable for milling machines, as it does not provide sufficient airflow or consistent line pressure.


15 Amp Power (Furnaces)

If the 15 amp outlets are not installed prior to delivery, we will still unpack and provision the furnaces.You can connect them once power is available, and we will guide you over the phone to load the required programs.


Pre-Installation Check

We will contact you 5 business days prior to installation to confirm all site requirements are met. This will include photographs of the requirements fulfilled. If anything is not ready, we will recommend delaying installation until all trades and requirements are complete. This ensures a smooth setup with minimal interruptions.


Installation Process

Day 1 – Installation & Setup

  • Our engineer and sales representative will arrive on site

  • All equipment will be unpacked and installed

  • Systems will be provisioned, tested and calibrated

  • Calibration targets and sample restorations will be milled


Your involvement on this day is minimal. We handle the full setup.


Day 2 – Training

  • Software and hardware training

  • CAM, manufacturing and post-processing workflows

  • Maintenance and daily operation


Do not plan to mill real cases on Day 1 or 2 or bring cases to run. We will release the system for clinical use only after training is complete and all design requirements for part milling is outlined. This is to ensure you are set up for consistent, unattended success from the start, not early failures. Clear communication, proper planning and having all site requirements in place ahead of time will ensure the smoothest possible installation. Our team will guide you through each step and do everything we can to make the process straightforward.


Our goal is simple: to get your UP3D milling system installed, running reliably and producing consistent results, with you fully confident to use it in your clinic or lab.


 
 
bottom of page